The engineering assurance record for a safety-assured fork of the reBot-DevArm desktop robot arm: machinery risk assessment under ISO 12100 and ISO 10218, a hardwired safety chain with a Performance Level target, collaborative-operation limits, cybersecurity and machine-learning safety, and a safety case published as it is built.
Built on Seeed Studio's reBot-DevArm. For the arm itself (assembly, bill of materials, software, tutorials) see upstream's repository and documentation.
Documentation · Wiki · Record status · Architecture · Standards · Roadmap · Known gaps · Getting started · Contributing · Upstream reBot-DevArm
The reBot Arm B601-DM is an open mechanical and actuator design with a broad software ecosystem, sold as a kit for embodied-AI research and teaching. What it lacks, by the fork's own concept-phase review, is the safety engineering a machine needs before it may work with a person in reach: there is no emergency stop in the documented design, no supply disconnect or fuse, no watchdog between the host and the actuators, no operating-mode state machine, no declared joint limits, no reliability data, no force or pressure measurement, no validation, and the software lives outside the fork. This fork keeps upstream's design and adds the record around it, under the standards that apply to an industrial robot.
The concept-phase engineering package the fork published first (reBot_DevArm_Safety_Case.xlsx and its companions
in this folder: 34 hazards, 31 safety functions, 28 gaps, 104 requirements, 127 test cases) is the input to
the record; its identifiers are kept and its gaps are re-stated as GAP-01 to GAP-36.
Every work product lives under assurance/, numbered in lifecycle order, with a
document-control header that says what it is, which clauses it answers to, and whether anyone has reviewed it.
Nothing is marked complete before its review, and every number below is computed from the records by
make_assets.py and checked by CI on every pull request.
P0 Governance · no gate passed · 90 work products (30 draft, 60 skeleton, 0 approved) · 36 gap findings (19 high) · 3 decisions open · 1 of 11 cross-domain interfaces open · 0 of 22 confirmation measures performed · records digest 5bd183fe53cb
| What the card guarantees | |
|---|---|
| A gate counts as passed | only when its record in 10-safety-case/gates/ says Pass; a skeleton generated from the process model is not a record |
| A work product counts as approved | only after a verification review by someone other than its author (WP-P-05); a confirmation measure counts only by its record under confirmation/ |
| The Living Safety Case dashboard | is generated from the records in assurance/case/: claims, evidence with review state, defeaters, actions, configurations and reviews, with a validator that refuses an accepted claim whose evidence is not available and accepted or whose defeater is open |
| The records digest | identifies the exact state of the register, the gap assessment, the decision register, the process model and the gate and confirmation records these figures describe, so two readers can confirm they saw the same state |
Development · baseline BL-001 at 206ebda · 21 claims (0 with accepted evidence) · 20 evidence items (0 accepted) · 36 open defeaters · records digest b6ab708350b6
Start here: assurance strategy (WP-M-01) · safety plan (WP-M-02) · process model and maps (WP-P-11) · powered-test hold point (WP-V-07) · decision register
Assurance status represents recorded engineering evidence and review state. It does not constitute certification or approval for operation with a person in reach.
The argument is a doer-and-checker argument with one more step. The host stack proposes; the controller safety layer checks; and a hardwired safety chain is the checker of last resort that nothing in software can override. Only the chain carries a Performance Level target. The safety layer and the host stack are hardened so that the chain is rarely demanded, and recorded as defence in depth.
| Layer | Role | State |
|---|---|---|
| Host stack | The SDK, the ROS 2 driver, Pinocchio, the LeRobot policies, the web UI; everything that decides where the arm goes | Inherited and upstream; hardening proposed once forked (DQ-007) |
| Controller safety layer | Validates, clamps, times out and reports every command before it reaches the motor bus; the mode machine | Does not exist yet. Where it runs is DQ-020 |
| Hardwired safety chain | Emergency stop, enabling, manual reset, power removal by contactor | Does not exist yet. Bench version first (WP-V-07, DQ-006), product version in the SRP/CS architecture |
| Safety and assurance | Risk assessment, safety functions and PLr, PL calculation, validation, cybersecurity, safety case | Draft and skeleton work products, not yet reviewed |
More in the architecture overview and WP-M-01 §6.
The arm is machinery and an industrial robot, so the frame is the machinery set, applied with one method: one hazard log, one requirements database, generated figures, a safety case with its defeaters published. Work products are structured after these standards and cite their clauses; no compliance is claimed, because no assessment has been performed and no standard is held. WP-M-01 §4 explains how each standard is used and where it is tailored; the wiki's How we use each standard is the plain-language version.
| Topic | Standard | Main work products |
|---|---|---|
| Risk assessment and reduction | ISO 12100:2010 | Item definition · Risk assessment · Risk reduction concept |
| Industrial robots and robot applications | ISO 10218-1:2025, ISO 10218-2:2025 | Safety functions and required PL · Operating envelopes |
| Collaborative operation | ISO/TS 15066:2016 | Human-robot interaction · Collaborative operation validation |
| Safety-related parts of control systems | ISO 13849-1:2023, ISO 13849-2:2012 | SRP/CS architecture · PL calculation · Safety validation |
| Where ISO 13849 runs out | IEC 62061:2021, IEC 61508:2010 | Software safety requirements · Confirmation measures |
| Electrical equipment, emergency stop, gaps and distances | EN 60204-1:2018, ISO 13850:2015, ISO 13854:2019, ISO 13855:2024, ISO 13857:2019 | Electrical safety · Mechanical analysis · Stopping and separation budget |
| Cybersecurity | IEC 62443-4-1:2018, IEC 62443-4-2:2019 | Threat and risk assessment · Cybersecurity plan |
| Machine learning in safety functions | ISO/IEC TR 5469:2024 | ML component definition · ML safety plan |
| Regulatory | Regulation (EU) 2023/1230 (Machinery), Regulation (EU) 2024/1689 (AI Act) | Regulatory conformity strategy |
| Safety case structure | UL 4600 principles | Safety case |
| Supporting practice | Where it is applied |
|---|---|
| Integrated process model | WP-P-11: activities, lanes, cross-domain interfaces and gates as data; generated swimlane maps and gate skeletons |
| Process capability | ASPICE self-assessment, WP-M-12 |
| Performance limits of sensing and the learned policy | ISO 21448 used as a method, not a standard, in the insufficiency analysis |
| Safety analysis | FMEA · FTA · CCF · STPA · Independence of the chain |
| Independent review | Confirmation measures plan · Verification and review procedure |
| Decisions | Decision register: every question for the project lead, self-contained, in batches of ten |
Status is taken from what exists in the repository. "Draft" means written but not reviewed; "skeleton" means the structure and clause map exist and the content is still to be written.
| Phase | Work | Status |
|---|---|---|
| 1 · Foundation | Assurance strategy, safety plan, confirmation measures, regulatory strategy | Draft |
| Baseline gap assessment | Draft | |
| Work product register, process model and maps, decision register | Draft; checked by CI | |
| Living Safety Case records and dashboard | Draft: records at BL-001, validated and drawn by CI | |
| 2 · Safety engineering | Item definition, operating envelopes, risk assessment, safety functions and PLr, interaction and misuse | Draft, from the concept-phase package |
| Risk reduction concept, insufficiency analysis, cybersecurity threat assessment, ML component definition | Skeleton | |
| Powered-test hold point | Draft; the bench chain waits on the lead (DQ-006) | |
| 3 · Build and verify | Bench safety chain, software fork and safety layer, chain architecture and PL calculation, stopping and holding tests, fault injection | Planned |
| 4 · Validate and release | Safety validation, assessment, technical documentation, release record, field monitoring | Planned |
The project publishes its own counter-evidence. The baseline gap assessment reviewed the hardware record and the concept-phase package, finding by finding, against the standards above. The findings that shape everything:
| Finding | Closes through | |
|---|---|---|
| GAP-08 | No emergency stop exists in the documented design; the only stop is a software command on the motor bus | The bench chain before any powered test with a person in reach (WP-V-07, DQ-006); the hardwired chain (WP-S-03) |
| GAP-09, GAP-11 | No supply disconnect or fuse; an open-frame mains supply with exposed terminals | Electrical safety (WP-H-05) |
| GAP-16, GAP-17, GAP-18 | The software is outside the fork; no mode machine; a lost connection holds the last command | Fork the software (DQ-007) and build the controller safety layer (WP-W-03) |
| GAP-19, GAP-02, GAP-03 | No declared joint limits, end-stops, mass or fixing | Mechanical analysis (WP-H-08) and the parameter sets (WP-W-09) |
| GAP-28, GAP-06 | No force or pressure measurement; no separation-distance plan | The collaborative-operation decision (DQ-005) and its validation (WP-V-03) |
| GAP-22, GAP-23 | Anyone with the CAN adapter or the network can move the arm | Cybersecurity requirements and architecture (WP-C-08, WP-S-07) |
| GAP-14, GAP-31 | No reliability data, no validation of any safety function | Supplier data (DQ-019), the PL calculation (WP-H-04) and the validation plan (WP-V-01) |
Every finding becomes a defeater against a claim in the safety case and stays open until the work product that closes it is reviewed.
Fifteen hazards of the risk assessment are drawn on upstream's v1.1 CAD, posed by a joint rig at the moment the hazard occurs, with a person where the interaction analysis puts them and the link gap or distance against the ISO 13854 minimum gaps beside the package's rating and the stop functions that do not exist yet (WP-P-12, gallery). They are pictures for review: synthetic, no evidence credit, and nothing in the safety case rests on them.
Only Python 3 is needed (PyYAML for the decision register):
git clone https://github.com/jherrodthomas/reBot-DevArm.git
cd reBot-DevArm
python3 assurance/01-management/decisions/check_decisions.py # the questions for the lead
python3 assurance/process/tools/process_model.py --check # process maps and gate skeletons current
python3 assurance/tools/folder_index.py --check # folder indexes match the register
python3 docs/assets/rebot/make_assets.py --check # README figures match their generator
python3 tools/wiki/build_wiki.py # the wiki pages check cleanOn an arm: the fork publishes no software build and changes no hardware yet. No arm is powered with a person inside its 650 mm reach under the fork's control until the conditions of WP-V-07 hold: a fused and switched 24 V supply, a dual-channel emergency stop through a safety relay, the arm fixtured, pinned software with the watchdog on, and nobody but the operator at the bench.
Contributions are welcome in machinery and robot safety, safety-related control systems, electrical and mechanical engineering, embedded and ROS 2 software, cybersecurity, verification, documentation and review. Safety-relevant changes need a rationale, an impact analysis and appropriate verification.
| Contributing | Rules for safety-relevant changes and assurance records |
| Issues · Pull requests | Problem reports, safety concerns, reviews of the analyses; pull requests target main |
| Security policy | Private vulnerability reporting |
| Wiki | Orientation: processes, process maps, how each standard is used, glossary, how decisions are made. Kept in wiki/ and mirrored on merge |
| Upstream reBot-DevArm | The arm this fork is derived from |
The package of 2026-05-04 stays at the repository root as the record's input; the files are not edited.
| File | Purpose |
|---|---|
reBot_DevArm_Safety_Case.xlsx |
15-tab preliminary safety case (ISO 12100 / 10218 / TS 15066 / 13849 / 9001 / 60204-1): 34 hazards, 31 safety functions, 28 gaps |
reBot_DevArm_Safety_Case_Report.docx |
Narrative safety case |
reBot_DevArm_Safety_Case_Summary.pdf |
2-page executive summary |
reBot_DevArm_DFMEA.xlsx |
AIAG-VDA 2019 DFMEA: 27 failure modes (11 high action priority) |
reBot_DevArm_Requirements.xlsx |
SyRS, SRS and HwRS: 104 requirements, traced |
reBot_DevArm_Architecture.docx |
5 architectural views with embedded diagrams |
reBot_DevArm_TestPlan.xlsx |
V-model test plan: 127 cases, ISO 13849-2 and TS 15066 V&V matrices |
reBot_DevArm_Trace_Memo.docx |
Cross-package traceability verification |
reBot_DevArm_Engineering_Bundle.pdf |
Single-file stakeholder bundle |
01_hero_banner.png … 05_mode_fsm.png |
The package's banner, KPI, envelope and architecture figures |
Jherrod Thomas maintains this record as an open engineering initiative: a public demonstration of safety-lifecycle development, systems engineering and assurance practice on a real robot arm.
reBot-DevArm is designed and published by Seeed Studio under
CC BY-NC-SA 4.0. This fork keeps that licence for the whole repository, including the record, and is non-commercial;
hardware/ is upstream's record, merged and never edited here. The fork is an independent project and is not
affiliated with or endorsed by Seeed Studio; it carries no reBot trademark claim.
Open-source licensing does not establish machinery safety certification, CE marking, or suitability for operation with a person in reach.